A SELECTION OF PICTURES FROM WEEK 17 OF NEW BUILD PROGRAMME

  • FIRST FLOOR LIFT

    Rebar laid ready for the concrete pour to make the floor in the first floor Art Department

    WEEK17.2.jpeg
    2975
    FIRST FLOOR LIFT
    Rebar laid ready for the concrete pour to make the floor in the first floor Art Department
  • DRAMA CORRIDOR

    Looking down the drama corridor towards the new main entrance

    WEEK17.10.jpg
    2977
    DRAMA CORRIDOR
    Looking down the drama corridor towards the new main entrance
  • BOILER ROOM

    Looking at the new boiler room . Casing built and rebar laid ready for the concrete flooring

    WEEK17.9.jpg
    2978
    BOILER ROOM
    Looking at the new boiler room . Casing built and rebar laid ready for the concrete flooring
  • REAR PLAYING FIELD

    Relandscaped rear playing field. This will allow us to have a second grassed playing pitch as well as the new 3G ATP

    WEEK17.8.jpg
    2979
    REAR PLAYING FIELD
    Relandscaped rear playing field. This will allow us to have a second grassed playing pitch as well as the new 3G ATP
  • 3G ALL WEATHER TRAINING PITCH

    Foundations levelled and laid. Fencing delivered and ready to be installed around the outside of the new pitch.

    WEEK17.7.jpg
    2980
    3G ALL WEATHER TRAINING PITCH
    Foundations levelled and laid. Fencing delivered and ready to be installed around the outside of the new pitch.
  • MUSIC DEPARTMENT

    Looking down onto the new music department and roof of the junior hall .

    WEEK17.5.jpg
    2982
    MUSIC DEPARTMENT
    Looking down onto the new music department and roof of the junior hall .
  • FIRST FLOOR

    First floor of the Art Department ready for the concrete pouring which will form the new floor.

    WEEK17.3.jpeg
    2984
    FIRST FLOOR
    First floor of the Art Department ready for the concrete pouring which will form the new floor.